Week 2 Progress

 In Belton House

Work is continuing in Section 4 this week, with the majority of the district heating pipe installed in the trenches. The manifold cupboard excavation is also 50% complete now. 

The new pipework in the shop has been fully completed and both The Stables and the shop have been re-plumbed to work with the new biomass system. 

Work will now start on Section 5, which will include installing new pipework into the Bookshop, Discovery Centre and The Ride.

 

 

Read more about the Belton House Project here