Week 8 Progress

 In Belton House

The foundations have now been laid for the biomass building, after the site was cleared last week. You can see the progress photos below:

 

As a recap from the last couple of weeks:

  • Sections 6, 7 and 1 are now 100% complete

  • Cottages termination is 100% complete

  • Offices termination is 100% complete

Section 2 will start this week and involves trenching through the main road in front of Belton House, to install the ducts which will carry the heating equipment from the biomass boilers to the buildings within the Belton House site. Check back next week for the progress on this!

Read more about the Belton House Project here